Martha Has Taken on an Ambitious Project That Requires Input

Question 9

Multiple Choice

Martha has taken on an ambitious project that requires input from different departments within the organization she works for. She also needs contributions from external experts and contractors. She needs to bring the work of all these groups together in a harmonious whole for the project. In the given scenario, Martha needs to engage in _____.


A) systems engineering
B) integration management
C) scope creep
D) suboptimization
E) conscious capitalism

Correct Answer: