The Majors Company Collected the Following Information (In Days) -
What Is the Manufacturing Cycle Efficiency?
A) 61

Question 7

Multiple Choice

The Majors Company collected the following information (in days) :
 Inspecting product 4 Transporting product 6 Storing product 15 Marufacturing product 40\begin{array} { | l | r| } \hline \text { Inspecting product } & 4 \\\hline \text { Transporting product } & 6 \\\hline \text { Storing product } & 15 \\\hline \text { Marufacturing product } & 40\\\hline\end{array}
-
What is the manufacturing cycle efficiency?


A) 61.5%.
B) 72.7%.
C) 87.0%.
D) 27.3%.