Essay
High Tech builds fence panels to custom order. Materials include 15 units of lumber at $2.25 per unit. Standards call for 3 hours of labor at $25 per hour.
During October, 3,121 fence panels were built. Materials purchased totaled $113,650 for 51,100 units of lumber. Actual lumber usage in production was 51,069 units. The October payroll was $248,000 for 9,500 hours.
Required:
(Be sure to indicate whether the variance is favorable or unfavorable.)
a. Compute the direct material price variance.
b. Compute the direct material efficiency variance.
c. Compute the direct labor rate variance.
d. Compute the direct labor efficiency variance.
Correct Answer:

Verified
a.$113,650 − (51,100 × $2.25) ...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q80: There are several reasons why actual results
Q81: For a company that produces more than
Q82: The labor yield variance is actual total
Q83: Professional accounting firms could not compute a
Q84: The Becton Enterprises (BE) produces a
Q86: A manufacturer of industrial equipment has
Q87: A company's direct labor standards for a
Q88: Maxine Watters, the managerial accountant, has been
Q89: A company makes a product using
Q90: Resolution Company is meeting with the consultants