The Following Information Summarizes the Standard Cost for Producing One

Question 136

Multiple Choice

The following information summarizes the standard cost for producing one metal tennis racket frame at Spaulding Industries. In addition, the variances for one month's production are given. Assume that all inventory accounts have zero balances at the beginning of the month.
 Standard Cost Per Standard Monthly  Uunit Costs Materials $4.00$8,400 Direct Labor 2 hrs @ $2.60 5.2010,920 Factory Overhead:  Variable 1.803,780 Fixed 5.0010,500$16.00$33,600\begin{array}{lcc}&\text { Standard Cost Per }&\text {Standard Monthly }\\&\text { Uunit}&\text { Costs}\\\text { Materials } & \$ 4.00 & \$ 8,400 \\\text { Direct Labor 2 hrs @ \$2.60 } & 5.20 & 10,920\\\text { Factory Overhead: } & & \\\text { Variable } & 1.80 & 3,780 \\\text { Fixed } & \underline{5.00} & \underline{10,500}\\& \underline{\$16.00}& \underline{\$33,600}\end{array}

 Variances:  Material price $244.75 unfavorable  Material quantity $500.00 unfavorable  Labor rate $520.00 favorable  Labor efficiency $2,080.00 unfavorable \begin{array}{llrl}\text { Variances: }\\\text { Material price } & \$ 244.75 & \text { unfavorable } \\\text { Material quantity } & \$ 500.00 & \text { unfavorable } \\\text { Labor rate } & \$ 520.00 & \text { favorable } \\\text { Labor efficiency } & \$ 2,080.00 & \text { unfavorable }\end{array}
-
What were the actual direct labor hours worked during the month?


A) 5,000
B) 4,800
C) 4,200
D) 4,000