Multiple Choice
Scallon Products reports the following information about resources. At the beginning of the year, Scallon estimated it would spend $8,000 for energy and $12,000 for repairs.
-
The unused resource capacity for repairs for Scallon Products is:
A) $2,400.
B) $12,000.
C) $6,000.
D) $3,600.