    Use the Earned Value Table (All Amounts Indicated Are Dollars)
Solved

Use the Earned Value Table (All Amounts Indicated Are Dollars)

Question 57

Question 57

Multiple Choice

Use the earned value table (all amounts indicated are dollars) to determine the earned value to the nearest hundred dollars given the indicated state of the project. Use the earned value table (all amounts indicated are dollars)  to determine the earned value to the nearest hundred dollars given the indicated state of the project.   A)  $16,900 B)  $14,900 C)  $14,400 D)  $13,200


A) $16,900
B) $14,900
C) $14,400
D) $13,200

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q7: If significant deviations from the project plan

Q8: A project manager can calculate the projected

Q17: What are any four benefits to using

Q20: Earned value is:<br>A)The total budget for the

Q29: A project manager can calculate the projected

Q34: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6815/.jpg" alt=" -Use the S-curve

Q54: Very short work packages would be better

Q58: Use the earned value table to determine

Q85: The earned value to date divided by

Q97: An unmotivated team is a key success

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines