Essay
A project manager ascertained that five different resources are needed to complete a project that has been estimated to last 37 days. Just to be on the safe side, the project manager told the client that the project would definitely be delivered in 40 days and 40 nights and arranged to rent the resources for that period of time. The project manager goes to the local rental center at the start of day 1 of the project, signs a 40-day lease agreement for all five resources, and brings them to the site to begin the project. Analyze the Gantt chart and resource list (activity durations are in parenthesis) and determine how much money is being wasted with this rental plan. If each resource could be rented for just the time it takes to complete each activity, what would the charge to the project be?
Correct Answer:

Verified
The project manager has paid for 40 days...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q3: If an activity's cost is plotted against
Q11: Quite often the marginal gains in employee
Q42: The fastest completion time for this project
Q46: AON networks have an advantage over AOA
Q48: The heir to the throne was due
Q49: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB7704/.jpg" alt=" -Use the Gantt
Q49: What are four criticisms and caveats to
Q50: Dummy activities are used in AOA networks
Q52: Crashing costs for a project are governed
Q62: An activity on an arrow network:<br>A)Cannot have