menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Project Management Achieving Competitive Advantage
  4. Exam
    Exam 10: Project Scheduling: Lagging, Crashing, and Activity Networks
  5. Question
    The AOA Network Described by This Table Needs
Solved

The AOA Network Described by This Table Needs

Question 71

Question 71

Multiple Choice

The AOA network described by this table needs: The AOA network described by this table needs:   A)  Zero dummy activities. B)  One dummy activity. C)  Two dummy activities. D)  Three dummy activities.


A) Zero dummy activities.
B) One dummy activity.
C) Two dummy activities.
D) Three dummy activities.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q15: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6815/.jpg" alt=" -What is the

Q19: Gantt charts cannot depict float.

Q29: Finish to start lags are the same

Q43: Sketch a network and use it as

Q64: Research has shown that,in general:<br>A)There is a

Q67: A project has the activity duration and

Q68: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB7704/.jpg" alt=" -Use the Gantt

Q73: A project has the activity duration and

Q74: The AOA network described by this table

Q83: Gantt charts can display early start or

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines