Multiple Choice
Use the information in the table to determine the slack time for Activity B.
A) 6 days
B) 4 days
C) 2 days
D) 0 days
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q8: An activity has an optimistic time estimate
Q32: What does a network diagram illustrate and
Q48: What is the early finish time for
Q52: What is the slack time for activity
Q54: Ray's shipment of materials hit every red
Q54: A gentleman farmer maniacally works on academic
Q75: Serial activities are those that:<br>A)Flow from one
Q82: An activity has an expected duration and
Q86: The least amount of float is found:<br>A)In
Q98: What are hammock activities and when should