Question 26

Multiple Choice

A project has the precedence requirements and activity durations shown in the table. After he draws the network, the project manager decides that activities E and F can be represented by a hammock activity. What are the duration and the early start time associated with this hammock activity? A project has the precedence requirements and activity durations shown in the table. After he draws the network, the project manager decides that activities E and F can be represented by a hammock activity. What are the duration and the early start time associated with this hammock activity?   A)  13, 36 B)  7, 0 C)  13, 7 D)  7, 14


A) 13, 36
B) 7, 0
C) 13, 7
D) 7, 14