Multiple Choice
A project has the precedence requirements and activity durations shown in the table. After he draws the network, the project manager decides that activities E and F can be represented by a hammock activity. What are the duration and the early start time associated with this hammock activity?
A) 13, 36
B) 7, 0
C) 13, 7
D) 7, 14
Correct Answer:

Verified
Correct Answer:
Verified