Multiple Choice
In an activity- on- node (AON) network, the nodes represent whereas the arcs represent .
A) precedence relationships; time
B) activities; time
C) activities; precedence relationships
D) events; activities
Correct Answer:

Verified
Correct Answer:
Verified