Before Beginning to Create a PERT/CPM Network Model for a Project

Question 9

Multiple Choice

Before beginning to create a PERT/CPM network model for a project, the project must be described in general terms. Two types of information that must be defined are


A) activities and precedence relationships.
B) crash times and manpower allocation.
C) slack time and activities.
D) manpower allocation and project due date.