Multiple Choice
Activity slack is defined as
A) earliest finish time minus latest finish time.
B) earliest start time minus latest start time.
C) latest start time minus earliest start time.
D) latest finish time minus earliest start time.
Correct Answer:

Verified
Correct Answer: