Multiple Choice
Table
A company uses a kanban system. The daily demand for part A is 4000 units. The average waiting time for a container of parts is day. The processing time for a container of part is day, and a container holds 300 units.
-Use the information in Table 8.3. How many kanban containers would be required if a 15 % efficiency factor is used?
A) 10 or less
B) 11 or 12
C) 13 or 14
D) 15 or more
Correct Answer:

Verified
Correct Answer:
Verified