Multiple Choice
Table
A toy company uses a kanban system to make a metal fastener that is a component of several toys. The waiting time for a container of the fasteners during production is day; average processing time is day per container. Each container holds 200 fasteners. The company uses 2000 fasteners a day in the production of its product.
-Use the information in Table 8.1. Using an efficiency factor of 5 %, calculate the number of kanban containers needed for the fastener.
A) 3 or less
B) 4 or 5
C) 5 or 6
D) the next person or machine to use or further the current process 7 or more
Correct Answer:

Verified
Correct Answer:
Verified
Q12: If infrequent,large shipments of purchased items are
Q21: The quality management tool called poka-yoke is
Q83: Table <span class="ql-formula" data-value="8.3"><span class="katex"><span
Q84: Discuss supplier relations as they pertain to
Q89: In lean systems, workers and first- line
Q90: Companies utilizing JIT systems generally have<br>A) suppliers
Q92: The _ method produces the item when
Q93: Which of the following statements regarding a
Q135: Explain how a line-flow strategy can be
Q138: _ is the philosophy that waste can