Solved

Table 8.18.1 A Toy Company Uses a Kanban System to Make a Make

Question 120

Multiple Choice

Table 8.18.1
A toy company uses a kanban system to make a metal fastener that is a component of several toys. The waiting time for a container of the fasteners during production is 0.250.25 day; average processing time is 0.150.15 day per container. Each container holds 200 fasteners. The company uses 2000 fasteners a day in the production of its product.
-Use the information in Table 8.1. How many kanban containers would be required if a 10 % efficiency factor is used?


A) 3 or less
B) 4 or 5
C) 5 or 6
D) 7 or more

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions