Multiple Choice
Continuous improvement with JIT systems
A) entails systematically stressing the system and focusing on problem areas.
B) requires periodically increasing lot sizes or workforce levels to uncover problems.
C) involves navigating a ship over treacherous rocks.
D) focuses exclusively on internal operations because relationships with customers and suppliers are addressed by the logistics department.
Correct Answer:

Verified
Correct Answer:
Verified