Multiple Choice
Table 13.3
Consider the following MPS, BOM, and inventory data. You will need a blank MRP record to answer the question(s) .
Master Production Schedule: the following table shows the MPS start quantities.
Week
Bill of Material
-End item A uses 1 each of component C and 1 each of subassembly D.
-Subassembly D uses 2 each of component E and 2 each of component F.
-End item B uses 1 each of component C and 2 each of component F.
Selected Inventory Data
Item
-Use the information in Table 13.3. Which one of the following statements about item F is TRUE?
A) Its first planned receipt is for 215 units in week 4.
B) There will be exactly one action notice, which calls for the release of a new order.
C) There will be exactly one action notice, which calls for the delay of the scheduled receipt until week 2.
D) The first planned order release is for 205 units in week 3.
Correct Answer:

Verified
Correct Answer:
Verified
Q157: The underlying logic for level- by- level
Q158: Part commonality refers to a degree to
Q159: Safety stock is more complex for independent
Q160: MRP explosion means estimating the total number
Q161: Complete the following MRP record in
Q163: Which one of the following statements about
Q164: The lot- for- lot lot sizing technique
Q165: _ is a lot- sizing rule
Q166: An end item is an item that
Q167: Which of the following statements about MRP