Planned Lead Time for Purchased Items Is

Question 80

Multiple Choice

Planned lead time for purchased items is


A) order processing time.
B) setup time plus materials handling time plus waiting time.
C) time difference between when the order was issued and when it would be received from the supplier.
D) setup time plus processing time plus waiting time.