Multiple Choice
Table 13.2.
-Use the information in Table 13.2. If the lot sizing was POQ (P = 3) instead of L4L, how many planned order releases would there be?
A) 0
B) 1 or 2
C) 3
D) 4 or more
Correct Answer:

Verified
Correct Answer:
Verified