Multiple Choice
If a planned receipt for an item is due in week 6 and the item's lead time is 2 weeks, in which week will the corresponding planned order release occur?
A) Week 2
B) Week 4
C) Week 6
D) Week 8
Correct Answer:

Verified
Correct Answer:
Verified