Table 13.8 Sunshine Manufacture Produces Three Products, X, Y, and Z. the Z

Question 137

Multiple Choice

Table 13.8
Sunshine Manufacture produces three products, X, Y, and Z. The production of these end items is controlled by an MRP
system. Each end item X is assembled with two components of A and one component of B. Each end item of Y is assembled
with two components of C and one component of A, each component of C is manufactured from one unit of B. End item Z is
assembled from one unit of D and one unit of C, D is manufactured from one unit of A, and C is manufactured from one unit
of B.
-Use the information in Table 13.8. If item C has a manufacturing lead time of two weeks and a planned receipt of 65 units is needed in week 4, which of the following statements is TRUE?


A) The planned order release in week 2 for item C is 130 units.
B) The gross requirements for item B in week 2 is 65 units.
C) The gross requirements for item B in week 2 is 130 units.
D) The gross requirements for item B in week 4 are at least 65 units.