a Company Is Attempting to Schedule Workers for the the Next

Question 114

Multiple Choice

Table 12.4
A company is attempting to schedule workers for the next seven days. The daily requirements, in number of workers needed,
are shown below.
 Day MTWTHFSSU Requirement 5484623\begin{array} { | r | c | c | c | c | c | c | c | } \hline \text { Day } & \mathrm { M } & \mathrm { T } & \mathrm { W } & \mathrm { TH } & \mathrm { F } & \mathrm { S } & \mathrm { SU } \\\hline \text { Requirement } & 5 & 4 & 8 & 4 & 6 & 2 & 3 \\\hline\end{array}
Each worker must work five days per week and must have two consecutive days off.
-Use the information in Table 12.4. How much total slack will be generated from the schedule?


A) less than 7 days
B) 7 days
C) 8 days
D) more than 8 days