Multiple Choice
Table 12.1
Gable Express Co. provides delivery service seven days a week.
The daily requirements (in workers) are estimated as follows:
Each worker is required to work five days per week,
and each must have two consecutive days off.
-Use the information in Table 12.1. How much total slack will be generated from the schedule?
A) less than 6 days
B) 6 days
C) 7 days
D) greater than 7 days