Multiple Choice
Table 10.18
A company desires to set up a line to produce 60 units per hour.
The work elements and their precedence relationships are as follows
-Use the information in Table 10.18. What is the theoretical minimum number of stations versus the number of stations required using the longest work- element time method?
A) 4 versus 6
B) 5 versus 6
C) 4 versus 5
D) 5 versus 5
Correct Answer:

Verified
Correct Answer:
Verified