Solved

Given the Following Data About an Assembly Line and the Knowledge

Question 133

Multiple Choice

Given the following data about an assembly line and the knowledge that we are trying to attain an output rate of 40 units per hour, what is the theoretical minimum number of stations?  Work  Element  Time (sec) 190280375470590685\begin{array} { | l | l | } \hline \begin{array} { l } \text { Work } \\\text { Element }\end{array} & \begin{array} { l } \text { Time } \\( \mathrm { sec } ) \end{array} \\\hline 1 & 90 \\2 & 80 \\3 & 75 \\4 & 70 \\5 & 90 \\6 & 85 \\\hline\end{array}


A) 4 or fewer stations
B) 5 stations
C) 6 stations
D) 7 or more stations

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions