A contractor and Buckingham, Inc.have a contract, which calls for the contractor to build a building with the completion of it by June 15.If the building is not completed by that date, the contract calls for the contractor to pay $100 per day in damages.The $100 per day is:
A) punitive damages.
B) nominal damages.
C) liquidated damages.
D) an illegal penalty.