  5. Question
    Once Managers Have Measured Actual Performance, They Should
Solved

Once Managers Have Measured Actual Performance, They Should

Question 69

Question 69

Multiple Choice

Once managers have measured actual performance, they should


A) revise accepted standards.
B) compare actual performance to the standards.
C) establish the standards of performance.
D) initiate corrective action.
E) develop goals and objectives.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q64: As a behavior control technique, direct supervision

Q65: Leverage ratios measure organizational performance based on

Q66: A customer service team identifies a goal

Q67: Describe Lewin's force-field theory. What causes an

Q68: When evaluating performance based on a revenue

Q70: An online clothing retailer discovered that the

Q71: A _ control technique accomplishes standardized behavior

Q72: As a regional manager, Maria's performance is

Q73: Explain the relationship between organizational control and

Q74: _ systems are the formal monitoring, evaluation,

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines