Multiple Choice
_________are risks that remain after avoidance, transfer, or mitigation strategies have been applied.
A) Outstanding risks
B) Enduring risks
C) Remaining risks
D) Residual risks
Correct Answer:

Verified
Correct Answer:
Verified