Multiple Choice
_________is a risk response strategy in which risks are simply accepted and contingency strategies are planned.
A) Risk acceptance
B) Risk contingency planning.
C) Risk adoption
D) Risk response
Correct Answer:

Verified
Correct Answer:
Verified