Multiple Choice
_________is the analysis of the probability of occurrence and impact of risk on project objectives using numerical techniques.
A) Quantitative risk analysis
B) Probability/impact risk rating matrix
C) Impact/likelihood risk rating matrix
D) Qualitative risk analysis
Correct Answer:

Verified
Correct Answer:
Verified
Q76: Risk management planning meetings should be attended
Q77: A tornado analysis shows, in descending order,
Q78: Events that serve as early warnings of
Q79: Project risk is an uncertain event or
Q80: The review of organizational information to aid
Q82: The process of identifying risks to a
Q83: Risk _ is concerned with the likelihood
Q84: Triggers are events that serve as early
Q85: Project risk is an uncertain event or
Q86: The systematic approach to planning the risk