Multiple Choice
All of the following are elements of a risk response plan EXCEPT:
A) a list of actions to be used to implement the risk response strategies.
B) the roles and responsibilities of any risk owners.
C) budget and schedule information in terms of risk response.
D) the roles and responsibilities of project stakeholders.
Correct Answer:

Verified
Correct Answer:
Verified