Multiple Choice
The estimation of activities' durations based upon the duration of similar activities is called:
A) similarity estimating.
B) psychometric estimating.
C) parametric estimating.
D) analogous estimating.
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q48: The sequence of activities:<br>A)can be determined without
Q49: _ is the measure of the
Q50: _ is the measure of the
Q51: Critical chain scheduling uses a _
Q52: Resources:<br>A)affect both the time and the cost
Q54: An example of parametric estimating is the
Q55: An activity on the critical path is
Q56: All of the following are techniques for
Q57: Managing resources should be considered:<br>A)during execution of
Q58: Published estimating data is a form of