The Process Used to Determine the Magnitude and Criticality of Schedule

Question 37

Multiple Choice

The process used to determine the magnitude and criticality of schedule variations is called:


A) criticality assessment.
B) order- of- magnitude estimation.
C) performance measurement.
D) critical path model.

Correct Answer:

verifed

Verified