Multiple Choice
________ is an estimating technique in which complex activities are further decomposed to a point where more accurate estimates can be made.
A) Expert judgment
B) Published estimating data
C) Alternatives analysis
D) Bottom- up estimating
Correct Answer:

Verified
Correct Answer:
Verified