Multiple Choice
Critical chain scheduling:
A) does not use feeding buffers.
B) is not concerned with resources.
C) eliminates all buffers from the project.
D) eliminates any buffers from individual activities to create a project buffer.
Correct Answer:

Verified
Correct Answer:
Verified