Multiple Choice
The estimation of activities' durations by averaging optimistic, pessimistic, and most likely estimates is called:
A) OPL- method.
B) likelihood procedure.
C) three- point estimates.
D) duration averaging.
Correct Answer:

Verified
Correct Answer:
Verified