Multiple Choice
A start- to- start dependency indicates that:
A) the completion of the successor activity depends on the beginning of the predecessor.
B) a second activity cannot be started until the first activity has been completed.
C) the start of a successor depends on the start of the predecessor.
D) the completion of the successor activity depends on the completion of the predecessor.