    Using a Bottom- Up Approach for Creating a WBS
Solved

Using a Bottom- Up Approach for Creating a WBS

Question 96

Question 96

Multiple Choice

Using a bottom- up approach for creating a WBS:


A) can be useful for novel projects.
B) helps to get buy- in from all group members.
C) is very time- consuming.
D) all of the above.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q91: During the planning stage, a project management

Q92: _dependencies indicate the relationship of project activities

Q93: Activity definition is the process of _and

Q94: _is the time delay between completion of

Q95: Work packages should be all EXCEPT:<br>A)completed by

Q97: Cone of uncertainty is a scheduling technique

Q98: A finish- to- finish dependency indicates that:<br>A)the

Q99: An activity can be performed by_ .

Q100: Work packages should all be about _.

Q101: The _is a diagramming method using boxes

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines