Multiple Choice
A finish- to- start dependency indicates that:
A) the completion of the successor activity depends on the completion of the predecessor.
B) the completion of the successor activity depends on the beginning of the predecessor.
C) the start of a successor depends on the start of the predecessor.
D) a second activity cannot be started until the first activity has been completed.
Correct Answer:

Verified