Multiple Choice
A diagramming method using arrows to represent activities and their precedence relationships, and nodes to represent project milestones is called:
A) box plot.
B) arrow diagramming method.
C) conditional diagramming method.
D) precedence diagramming method.
Correct Answer:

Verified
Correct Answer:
Verified