Short Answer
A____________ provides additional detail about the individual components of a WBS.
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q82: A WBS should always be presented as
Q83: A WBS can be deliverable- or _
Q84: A project can be broken down by
Q85: A WBS is the output that results
Q86: A_ dependency indicates that a second activity
Q88: Network_ are templates developed from previous projects
Q89: _are important dates within a project schedule
Q90: List the three forms of dependencies between
Q91: During the planning stage, a project management
Q92: _dependencies indicate the relationship of project activities