Multiple Choice
What is NOT a characteristic of a Gantt chart?
A) A Gantt chart shows the time overlap of tasks.
B) A Gantt chart clearly shows how tasks must be ordered.
C) A Gantt chart visually shows the duration of tasks.
D) A Gantt chart can visually show slack times available.
Correct Answer:

Verified
Correct Answer:
Verified