The shortest time in which a project can be completed is shown by the:


A) crucial path
B) critical path.
C) shortest path.
D) longest path.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q27: The fourth phase in the SDLC is

Q28: Structured system design that can be broken

Q29: The third phase in the SDLC is

Q30: The second phase of the systems development

Q31: The phases of managing a project are

Q33: Standards may over time become_ regulations, driven

Q34: Activity definition is part of which process

Q35: A_ organization structure is a traditional hierarchical

Q36: A functional organizational structure is sometimes thought

Q37: An organization's _reflects what those who work

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines