Multiple Choice
The technique that uses optimistic, pessimistic, and realistic time to calculate the expected time for a particular task is called:
A) PERT.
B) OPR technique.
C) PORT.
D) expected time technique.
Correct Answer:

Verified
Correct Answer:
Verified