    The Technique That Uses Optimistic, Pessimistic, and Realistic Time to Calculate
Solved

The Technique That Uses Optimistic, Pessimistic, and Realistic Time to Calculate

Question 54

Question 54

Short Answer

The technique that uses optimistic, pessimistic, and realistic time to calculate the expected time for a particular task is known as___________ .

Correct Answer:

verifed

Verified

Program Ev...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q49: Standards may become de facto regulations, driven

Q50: Systems implementation includes all EXCEPT:<br>A)testing.<br>B)coding.<br>C)installation.<br>D)maintenance.

Q51: Requesting seller responses is part of which

Q52: Most project life cycles share the following

Q53: The process group involving defining goals and

Q55: Activities with a slack time of zero

Q56: Specifications which focus on the origin, flow,

Q57: The process group involving coordinating people and

Q58: Describe the systems maintenance phase of the

Q59: A series of continuous actions that bring

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines