    The Critical Path Is the Shortest Path Though a Network
Solved

The Critical Path Is the Shortest Path Though a Network

Question 93

Question 93

True/False

The critical path is the shortest path though a network diagram.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q88: Managing the project team is part of

Q89: The first phase in the SDLC, where

Q90: The amount of time an activity can

Q91: Contract closure is part of which process

Q92: A type of organizational structure where people

Q94: Network diagrams are useful to visually show

Q95: The five phases of the systems development

Q96: Nodes not on the critical path contain_

Q97: Projects are divided into smaller parts called

Q98: The review points at the end of

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines