Multiple Choice
_________is the final implementation and training related to the project, getting acceptance and signoff on the project, and archiving of the project's results.
A) Project implementation
B) Project closure
C) Project signoff
D) Project handover
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q87: The _is calculated by dividing the BAC
Q88: When management ignores negative information, being reluctant
Q89: The cost baseline is a time- phased
Q90: Project closure is the final implementation and
Q91: _are requested changes that were not chosen
Q93: _is the management style the manager employs
Q94: What is project closure and why is
Q95: Reluctance to hear bad news communicated from
Q96: Pareto's law states that 80% of the
Q97: The_ is a time- phased budget that