Multiple Choice
_________is the process of identifying the cause of variance relative to the project baseline and determining whether any corrective action is needed.
A) Variance analysis
B) Cause and effect diagramming
C) Baseline analysis
D) Progress analysis
Correct Answer:

Verified
Correct Answer:
Verified