Multiple Choice
_________are documented and authorized guidelines necessary to bring future project performance in conformance with the project management plan.
A) Approved preventive actions
B) Approved change requests
C) Approved defect repair
D) Approved corrective actions
Correct Answer:

Verified
Correct Answer:
Verified
Q8: A change control system is a documented
Q9: _are items or activities that will still
Q10: _are documented recommendations that minimize the probability
Q11: _is the process of identifying the cause
Q12: Withholding negative information out of fear for
Q14: In addition to the philosophy of project
Q15: Cost control is the process of monitoring
Q16: For large, complex projects, the_ may be
Q17: Controlling processes are important factor in all
Q18: A _system is a formal, documented process